This chapter provides an overview of subcontracting using PeopleSoft Enterprise Manufacturing and discusses how to:
Select subcontracted operations for purchase order creation.
Manage purchase order changes.
Receive end items from vendors.
Record completed operations and scrap for subcontracted operations.
Move completed end items.
Complete production for subcontracted operations.
Edit or issue components for subcontracted operations.
Create reversing entries.
Record actual labor and machine hours.
In the shop floor environment, you may need to send components or end items to outside vendors for end item processing, rework, inspection, or testing. PeopleSoft Enterprise Manufacturing enables you to track production progress and outside processing vendor costs associated with subcontracting using production IDs.
Although managing production with subcontracted operations is similar to managing production for in-house production, there are some differences:
Once production has been released or started, you select production IDs with subcontracted operations and send the information to PeopleSoft Enterprise Purchasing where purchase orders are created.
You record operation completions for both in-house and, once the end items are received back from the vendor, subcontracted operations. Once the end items are complete at the final operation, they can be sent to stock or routed to another production area. If the completed end items are lot- or serial-controlled, you assign lot and serial numbers.
You determine how much lead time you need to generate and process a purchase order for the subcontracted operation.
If you are using electronic data collection for purchasing receipts, the system automatically generates the subcontracted completions transactions.
Note. You cannot perform a production ID split if you have run the Select Subcontract Prdn for PO process.
To manage production with subcontracted operations:
Record completed operations and scrap for in-house production for operation sequences prior to the subcontracted operation.
Use the Record Completions/Scrap component to make data entry corrections if required.
Use the Subcontracted PO Selection page to generate the file for subcontracted operations to be used by the Create Purchase Orders process (PO_POCREATE).
Generate the purchase order for outside processing, and approve and dispatch the purchase order to the vendor.
Use the PO Stage Load, PO Calculation, PO Creation, Approve Amounts, and Dispatch POs pages in PeopleSoft Enterprise Purchasing to process the subcontracted PO.
Send end items to outside vendors for subcontracted processing.
Receive end items back from vendors using the Receiving page in PeopleSoft Enterprise Purchasing.
See Processing Receipts.
Use the Subcontracted Receipt page to record completed subcontracted operations and scrap for the subcontracted item.
(Optional) Edit components.
Record completions and scrap for any additional in-house operations for the subcontracted end item.
See Recording Completions and Scrap Using Electronic Data Collection.
Move completed end items out of production.
Run the Completions Update process (SFPDCDRV).
Use the Complete Production page to indicate that production for all operations has been completed.
(Optional) Record actual labor and machine hours associated with the subcontracted operations.
Prior to scheduling a subcontracted operation:
Identify which tasks and operations are subcontracted.
You can't subcontract operations for configured items.
(Optional) Specify the vendor that will be performing the operation or task.
(Optional) Define queue and in-transit planning times for subcontracting tasks and operations.
You can also define setup, run, fixed run, and post production planning and costing times. These options permit accurate scheduling and costing of the subcontracted operations.
Designate components as subcontractor supplied on the BOM components page.
Define nonowned components and locations.
Define load defaults within PeopleSoft Enterprise Purchasing.
Release material to the shop floor for end items with subcontracted components and operations.
Create and release productions IDs for end items with subcontracted components and operations.
Determine how much lead time you need to generate and process a purchase order for the subcontracted operation.
Production ID |
The production order identifier. |
Production Area |
The production area identifier where the manufacturing process occurs. |
Item ID |
The name and description of the item being manufactured. |
Prdn Type (production type) |
The type of production: Production, Rework, or Teardown. |
BOM Code |
The BOM identifier used during the manufacturing process. |
Routing Code |
The routing identifier used during the manufacturing process. |
Revision |
The revision identifier if the item is revision-controlled. |
When part or all of the manufacturing process is done at an outside vendor, you need to generate purchase orders for production IDs with subcontracted operations. Use purchase orders to authorize a vendor to add labor or material or both to a partially completed end item.
Using the Select Subcontract Prdn for PO page in PeopleSoft Enterprise Manufacturing, you select one or more production IDs, production areas, or item IDs for which to generate purchase orders for subcontracted operations. When you run the Select Subcontract Prdn for PO process (SFS5000), the system automatically transfers the subcontracted operations information for purchase order creation to PeopleSoft Enterprise Purchasing, including production ID information for which the outside processing must be done as well as the operation sequence associated with the outside operation. Once the subcontracted purchase order is generated, it is processed like any regular purchase order within PeopleSoft Enterprise Purchasing.
To create purchase orders for subcontracted operations, verify that:
The production ID has a status of Released or In Process.
An operation list exists for the production ID.
Manually create an operation list if the production ID is for rework, you didn't specify a routing, or you choose not to copy the routing to the production ID.
Completing Operations and Scrap for Production Using Count Points
If you're using count points, then all subcontracted operations must be defined as count point.
Page Name |
Object Name |
Navigation |
Usage |
RUN_SFS5000 |
Production Control, Process Production, Subcontract Prdn for PO, Select Subcontract Production |
Select production that requires purchase orders for subcontracted operations. |
|
RUN_SFS2008 |
Production Control, Process Production, Subcontracted PO Report |
View the status of purchase orders that you've requested for subcontracted production. |
Access the Select Subcontract Production page.
Selection Criteria |
Select the options indicating the production to generate purchase orders for subcontracted operations. Options are:
|
Run |
Click to run this request. Process Scheduler runs the Select Subcontract PO for Prdn process (SFS5000) at user-defined intervals. |
Extract to PO only when prior Op Seq is complete |
Select this check box to ensure that the subcontract PO is created only after the prior operations are complete, thereby eliminating change orders. |
Once you run the Select Subcontract Prdn for PO process, the purchase orders for the subcontracted services can be generated.
To generate, approve, and dispatch the subcontracted purchase order:
Run the PO Stage Load process (PO_POSTAGE).
This process is run with the PO Stage Load page (Purchase Orders, Build/Source POs), takes all the requests generated from requisitions, PeopleSoft Enterprise Supply Planning, and PeopleSoft Enterprise Manufacturing, and stages them for the actual purchase order creation.
Run the PO Calculations process (PO_POCALC).
This process is an Application Engine process that does most of the processing to create a purchase order. Use the PO Calculations navigation to run this process.
Run the Create Purchase Orders process (PO_POCREATE).
This process is an Application Engine process that generates the purchase orders that will be staged for approval and dispatching. Use the PO Creation navigation to create purchase orders for the subcontracted service.
If a recommended vendor was listed on the subcontracted task or operation, the purchase order is created with the vendor specified. If the vendor field was left blank on the routing or operation list for the production ID, the suggested vendor, as defined in PeopleSoft Enterprise Purchasing, is selected.
The system-generated purchase order for the subcontracted service contains this data:
Business unit and production ID associated with the production.
Task description if a task code is associated with the subcontracted operation. Otherwise, the end item description is used, along with the prefix of SERVICE.
Quantity and unit of measure.
Operation sequence associated with the subcontracted operation.
Purchase order due date based on the due date of the subcontracted operation.
Purchase order unit price based on the cost defined for the subcontracted operation.
Once you've created the purchase orders, you must approve and dispatch them before you can send the purchase order to the vendor.
Use the Amount Approval and Dispatch Purchase Orders pages to approve and dispatch the purchase orders for the subcontracted operations.
See Also
SFS2008 - Subcontracted Purchase Order Report
Sometimes you may need to change a purchase order to respond to production changes. If a purchase order for subcontracting production has been created and a production change requires a change to the purchase order, PeopleSoft Enterprise Manufacturing sends a purchase order change request to PeopleSoft Enterprise Purchasing. This request indicates that a purchase order change is required for the subcontracted purchase, and either a purchase order change request is processed or a new purchase order needs to be generated.
You may also need to change the purchase order when any end items have been returned from the vendor as scrap.
A purchase order change may be necessary when there is a change to:
The production quantity.
A quantity change can result from production maintenance as well as from scrapping end items when you're recording completions.
The actual start date and time or actual due date and time for the production IDs or subcontracted operation.
The purchase order change request is processed by PeopleSoft Enterprise Purchasing using the Change Order Request page.
After you request a purchase order and run the PO Stage load process, the subcontracted operation has an In Process status, after PeopleSoft Enterprise Purchasing has received and acknowledged the subcontracted operation information.
If you use the background reschedule process to reschedule production with subcontracted operations, and the purchase order date is no longer valid, the system cannot reschedule an In Process purchase order. When running the background reschedule process, you can request that the system check for any production that has an In Process purchase order for subcontracted operations. In this case, the system displays an error message for each instance, unless you decide to skip further in process messages. You can then contact the purchasing department to reschedule the purchase order.
If you cancel or delete the subcontracted PO, line, or schedule, the system resets the subcontracted PO status for the associated production ID or operation sequences associated with the PO, line, or schedule. Therefore, you need to rerun the process to generate a subcontracted PO.
Receiving end items back from a vendor is a two-step process:
Receiving records the receipt of the end items back from the vendor.
Production records the operations completions and scrap for the received end items.
Once the vendor has completed the subcontracted work, the end items are returned to Receiving. To receive end items back from the subcontractor, use the Receive with Purchase Order page.
During the receiving process, the end items can be inspected and accepted or rejected from the vendor. Receiving assigns one of these indicators to the rejected quantity when recording the receipt:
Return for Replacement |
Return the end item to the vendor with the expectation that it will be replaced. The return quantity is equal to the reject quantity with a reject action of Return to Replacement. The received rejected quantity at the production is the received quantity and the received rejected quantity is zero. PeopleSoft Enterprise Purchasing does not record the replacement quantity as either accepted or rejected. |
Return for Credit |
Return the end items back to the vendor for a credit. The credited amount is the subcontracted service charge. If the reject action is Return for Credit, it creates a return to vendor (RTV) record when you save the page. The return quantity is equal to the reject quantity with a reject action of Return for Credit. The RTV updates the return quantity on the receiver record. The action also updates the purchase order, and subtracts the quantity returned. PeopleSoft Enterprise Purchasing records the RTV quantity as scrap on the Production Subcontract Receiving page. |
This table summarizes the receiving reject actions and effects:
Action |
Receiving Record |
PS_RECV_SUBREC_MG |
PO Line |
Return for Replacement |
No reject qty |
No scrap |
No update |
Return for Credit |
Scrap the qty |
Scrap the qty |
Update |
Subcontracted receipts to stock are prevented if the end item or a component of the end item is on hold and the order is for regular production. Subcontracted receipts to intermediate operations are allowed for regular production.
The PeopleSoft Enterprise Purchasing receipt process updates production to indicate that the end items have been received. You cannot record operation completions or scrap until the end items have been received.
In addition, you cannot close production until the quantity of end items sent to the vendor is equal to the quantity of scrapped and completed end items received back from the vendor and recorded complete in production.
PeopleSoft Enterprise Purchasing can optionally receive end items using electronic data collection. Electronic data collection transactions for subcontracted end items automatically record the subcontracted completions data. You don't need to record completions in the Subcontracted Receipt pages for these subcontracted end items. After the transactions are recorded and staged, run the Completions/Scrap Update process to update the production balances.
Once you've processed the end items through receiving and inspection, you can record the operation as complete in PeopleSoft Enterprise Manufacturing. If the subcontracted operation is the last operation on the routing, you can also indicate that production is completed.
When you record scrap for the end item, the system optionally sends a workflow notification to selected roles defined by you. These roles might include a quality manager or a production control manager.
If you are integrating with a Manufacturing Execution System (MES), you can receive subcontracted operation completions from the MES to the PeopleSoft Enterprise system. The end items need to be received in PeopleSoft Enterprise Purchasing before you can record the completion transaction in PeopleSoft Enterprise Manufacturing. The MES sends the same information for a subcontracted completion as with completions for regular operations.
See Also
Integrating PeopleSoft Enterprise Manufacturing with a Third-Party System
PeopleSoft Enterprise Supply Chain Management Integration PeopleBook
Page Name |
Object Name |
Navigation |
Usage |
SF_SUBREC |
Production Control, Process Production, Subcontract Production, Receive Subcontract Assembly, Subcontracted Receipt |
Record completed operations and scrap by subcontracted operation. Note. You must receive the subcontracted end items through PeopleSoft Enterprise Purchasing before using this page. |
|
SF_COMPL_PRDN |
Production Control, Process Production, Subcontract Production, Receive Subcontract Assembly, Subcontracted Receipt Click the Complete Production link. |
Indicate that production is completed for production IDs with subcontracted operations. |
|
SF_RECEIPT_INFO |
Production Control, Process Production, Subcontract Production, Receive Subcontract Assembly, Subcontracted Receipt, Receipt Information |
View receipt and completions information about the subcontracted operation. |
|
SF_COMPL_ID |
Production Control, Process Production, Complete Production, Record Completions/Scrap |
(Optional) Enter completions and scrap information for production IDs. In addition, use this page to move end items for production IDs with a single output or multiple outputs. |
|
SF_COMPL_SCRAP |
Production Control, Process Production, Complete Production, Record Completions/Scrap Click the Enter Scrap Data link. |
Enter scrap quantities, if applicable. |
|
SF_COMPL_DEFAULTS |
Production Control, Process Production, Complete Production, Record Completions/Scrap Click the Apply Defaults link. |
Select the default putaway or alternate storage locations for the completed end items. |
|
AUTO_SERIAL_WRK |
Production Control, Process Production, Complete Production, Record Completions/Scrap Click the Generate Serial IDs link. |
(Optional) Automatically generate serial numbers for production end items that are serial-controlled. Note. You must define serial-controlled items in PeopleSoft Enterprise Inventory. |
|
SF_ED_CMP_SBP_GRD |
Production Control, Process Production, Complete Production, Record Completions/Scrap, Edit/Issue Express Click the Select Lot/Serial link. |
(Optional) Identify the lots from which you want to consume lot-controlled components. You must enter a pending quantity greater than zero for a lot-controlled component before the Lot/Serial scroll area is available. |
|
SF_TRANSHIST |
Production Control, Define Production, Review Production Information, Production History |
View production transaction history for production IDs. |
|
SF_TXN_HIST_SP |
Production Control, Define Production, Review Production Information, Production History Click the Detail button on the Production History page. |
View production transaction history details based on:
|
Access the Subcontracted Receipt page.
Print at Save |
Select this check box if you want to print production documents at save time. |
Setup Print Options |
Click this link to access the Process/Output Options page to select different print criteria for the production documents. |
Completed Qty (completed quantity) |
Enter the number of end items being completed. |
Quality |
Click this link to initiate a data entry session and to access either the Data Entry - Subgroup Method page or the Data Entry - Sample Method page in PeopleSoft Enterprise Quality, depending on the data entry method that you specified when creating the quality control plan. |
Operations Data
View display-only production data such as assembly start quantities, number of assemblies scrapped, expected completed quantities, and yield percentages for each operation sequence.
See Also
Access the Receipt Information page.
Recv Rejected Qty (received rejected quantity) |
Displays the quantity that Receiving rejected from the vendor and that was recorded in PeopleSoft Enterprise Purchasing. Receiving assigns one of these indicators to the rejected quantity:
Only received quantities that have a status of Return for Credit appear in this field. |
Prdn Accepted Qty (production accepted quantity) |
Displays the quantity that was actually recorded as a completion using the Subcontract Receipt page. |
Prdn Rejected Qty (production rejected quantity) |
Displays the quantity that was actually recorded as scrap using the Subcontract Receipt page. |
Note. Use the Edit Components page if you want to modify or view the components that will be consumed based on the quantity completed or scrapped, or if you need to select the serial or lot numbers for those serial- or lot-controlled components that were consumed when you recorded the completion.
The process for moving completed end items for subcontracted operations is the same as for other production.
See Moving Completed End Items and Assigning Serial and Lot Numbers.
The process for completing production for subcontracted operations is similar to the process for other production.
See Running the Completions Update COBOL/SQR Process (SFPDCDRV).
Page Name |
Object Name |
Navigation |
Usage |
SF_COMPL_SELECTION |
Production Control, Process Production, Complete Production, Record Completions and Scrap, Production Selection |
Select a production ID to record completions and scrap. |
|
SF_COMPL_ID |
Production Control, Process Production, Complete Production, Record Completions and Scrap |
Enter completions and scrap information for the production ID. |
|
SF_COMPL_PRDN |
Production Control, Process Production, Complete Production, Record Completions and Scrap Click the Complete Production link. |
Indicate that production at all operation sequences has been completed. |
The process for editing or issuing components for subcontracted operations is similar to that of other production.
Page Name |
Object Name |
Navigation |
Usage |
SF_EDIT_COMPS_EDIT |
Production Control, Process Production, Subcontract Production, Receive Subcontract Assembly, Edit/Issue Components Summary |
Edit or view components. |
|
SF_EDIT_COMPS_EXPR |
Production Control, Process Production, Subcontract Production, Receive Subcontract Assembly, Edit/Issue Express |
(Optional) Select lot- or serial-controlled components that have pending issue or pending loss quantities. |
|
SF_ED_CMP_SBP_GRD |
Production Control, Process Production, Subcontract Production, Receive Subcontract Assembly, Edit/Issue Express Click the Select Lot/Serial link. |
(Optional) Select the lot or serial numbers (or both) of the lot- or serial-controlled components to be consumed during the completions process. You must enter a pending quantity greater than zero for a serial-controlled or lot-controlled component before the Lot/Serial scroll area is available. |
|
SF_EDIT_COMPS_DET |
|
View detailed information for each component for selected production. |
|
SF_COMPL_SELECTION |
Production Control, Process Production, Complete Production, Record Completions/Scrap, Production Selection |
Return components issued during completions or to correct data entry errors. You can also return lot- or serial-controlled end items by using this page. Record completions for a production ID or a production schedule. To return lot- or serial-controlled end items, first record operations and scrap and put away production with lot- and serial-controlled components. |
|
SF_COMPL_ID |
Production Control, Process Production, Complete Production, Record Completions/Scrap |
Return components issued during completions or to correct data entry errors. You can also return lot- or serial-controlled end items by using this page. |
|
SF_TRANSHIST |
Production Control, Define Production, Review Production Information, Production History |
View production transaction history for components. |
|
SF_TXN_HIST_SP |
Production Control, Define Production, Review Production Information, Production History Click the Detail button. |
View completions details based on the selection criteria. |
If a data entry error is made when recording end item completions or scrap for a subcontracted operation, input a negative number to reverse the completion or scrap entry. For example, an entry was made to record a completion of eight end items at operation 20, but only six end items were actually completed. Enter a -2 in the Completed Qty field to reverse the original entry of 8. This brings the completed quantity balance for that operation to 6.
This reversing entry:
Rebalances the completions or scrap count.
Rolls back the reversing entry only through the subcontracted operation.
Automatically returns any components that were consumed at the current operation to the appropriate WIP location.
Creates a reversing entry for earned labor, machine, and overhead costs.
Creating a Reversing Entry for Subcontracted Operations Using Count Points
If you are performing reversing entries for production IDs with subcontracted operations, you can reverse operations and scrap from one count point (or subcontracted operation) to the prior count point (or subcontracted operation).
See Also
Moving Completed End Items and Assigning Serial and Lot Numbers
Page Name |
Object Name |
Navigation |
Usage |
SF_COMPL_SELECTION |
Production Control, Process Production, Complete Production, Record Completions and Scrap, Production Selection |
Select a production ID to create reversing entries. |
|
SF_COMPL_ID |
Production Control, Process Production, Complete Production, Record Completions and Scrap, Production Selection, Record Completions and Scrap |
Enter reversing entries for selected production. |
|
SF_COMPL_SCRAP |
Production Control, Process Production, Complete Production, Record Completions and Scrap, Production Selection, Record Completions and Scrap Click the Enter Scrap Data link. |
Enter any reversing entries to scrapped quantities, if applicable. |
|
SF_COMPL_DEFAULTS |
Production Control, Process Production, Complete Production, Record Completions and Scrap, Production Selection, Record Completions and Scrap Click the Apply Defaults link. |
Select the putaway locations for the reversing entries. |
|
Lot/Serial Number Selection |
SF_ED_CMP_SBP_GRD |
Production Control, Process Production, Complete Production, Record Completions and Scrap, Production Selection, Edit/Issue Express Click the Select Lot/Serial link. |
(Optional) Select the serial numbers of the serial-controlled components to be returned. |
Lot/Serial Number Selection scroll area |
SF_ED_CMP_SBP_GRD |
Production Control, Process Production, Complete Production, Record Completions and Scrap, Production Selection, Edit/Issue Express Click the Select Lot/Serial link. |
(Optional) Identify the lots from which you want to return lot-controlled components. |
The process for recording actual labor and machine hours for subcontracted production is similar to that of other production.
See Recording Actual Machine and Labor Hours.
Page Name |
Object Name |
Navigation |
Usage |
SF_ACTHR_SELECTION |
Production Control, Process Production, Complete Production, Record Actual Hours, Production Selection |
Select the production that you want to record actual machine and labor hours incurred during the production process. |
|
SF_ACTHRS_NEW |
Production Control, Process Production, Complete Production, Production Selection, Record Actual Hours |
Enter labor and machine hours for the selected production. |
|
SF_ACTHRS_INQUIRY |
Production Control, Close and Analyze Production, Review Actual Hours |
Select a specific production ID or production schedule to view actual labor and labor information. |
|
SF_ACTHRS_INQ_GRD |
Production Control, Close and Analyze Production, Review Actual Hours, Actual Hours by Operation |
View actual labor and machine hours for a production ID or schedule by operation. |
|
SF_ACTHRS_INQ |
Production Control, Close and Analyze Production, Review Actual Hours, Actual Hours Detail |
View detailed information on actual labor and machine hours for a production ID or schedule by operation. |
|
SF_ACTHRS_INQ_SEC |
Production Control, Close and Analyze Production, Review Actual Hours, Actual Hours Detail Click the Show Crew/Machine Resources button. |
View resource details for the crew or machine. |