This chapter provides an overview of the copy functionality in Proposal Management and discusses how to:
Copy proposal information.
Copy proposal versions.
Copy projects.
In Proposal Management, you use the Copy Proposal Process component (GM_BUD_PPSL_CPY) to copy proposals, versions, and projects. Use the:
Copy Proposal feature to copy versions to use in different proposals.
When you copy a new proposal from an existing proposal version, the system generates the new proposal, version, and project IDs. The system does not select the Create Resources Team check box when you initiate the Copy Proposal feature.
Copy Version feature to copy versions to use in the same proposal.
When you copy a version, the system generates a new version ID. The system uses the same proposal ID as the proposal version from which you are copying to prevent conflicting data when it generates the proposal into a contract.
Copy Project feature to copy projects to use in the same version.
When you copy a project, the new proposal ID and version ID match the proposal and version from which you are copying. The system generates the new project ID. Like the Copy Proposal and Copy Version pages, you can select activities and copy options on the Copy Project page. The system uses the same proposal ID as the project from which you are copying to prevent conflicting data when it generates the proposal into a contract.
This section discusses how to copy proposal information.
Page Name |
Object Name |
Navigation |
Usage |
GM_BUD_PPSL_CPY |
|
Copy proposal information to a new proposal. |
Access the Copy Proposal page.
To Proposal |
The word NEXT appears by default. When you click Copy, the system generates the next proposal ID that is available. |
To Version |
The word NEXT appears by default. When you click Copy, the system generates V101as the version ID. |
To Start Date and To End Date |
By default, the system populates the start and end dates of the proposal from which you are copying; however, you can change these values. If you change the start and end dates on the target proposal, the copy process changes the start and end dates for all of its projects and activities. |
Project
From Project ID |
Clear this check box for all the projects that you do not want to copy to the new proposal. |
To Project ID |
The word NEXT appears by default. When you click Copy, the system copies project and activity information to the next available project ID. |
Activity
From Activity |
Clear this check box for all the activities that you do not want to copy to the new proposal. |
To Activity |
The activity ID of the version from which you are copying appears by default. You can, however, select a new activity ID from the list of available choices. |
Copy Options |
Select a value to specify which information you want to copy to the proposal for the particular activity: Labor and Non-labor (system default), Labor, Non-labor, or None. |
Copy |
Click to initiate the copy process. |
This section discusses how to copy proposal versions.
Page Name |
Object Name |
Navigation |
Usage |
GM_BUD_PPSL_CPY |
|
Copy version information within the same proposal. |
Access the Copy Version page.
To Proposal |
Displays the current proposal ID from which you are copying the proposal version. You cannot change this field. The new version of the proposal must have the same proposal ID. |
To Version |
Displays the word NEXT. When you click Copy, the system generates the next available version ID for the proposal. For example, if the proposal has versions V101, V102, and V103 and you are copying version V101, the system automatically labels the new version V104. |
To Start Date and To End Date |
The system populates the start and end dates of the version from which you are copying. You cannot modify these fields. |
Project
From Project ID |
The system automatically selects all projects when you enter this page. Clear this check box for all the projects that you do not want to copy to the new version of the proposal. |
To Project ID |
Displays the ID of the project from which you are copying information. You cannot change the number in this field. The new project ID must always equal the copied project ID, so that there are no conflicting data issues when the proposal is generated into a contract. |
Activity
From Activity |
Select this check box for all the activities that you want to copy to the new version of the proposal. |
To Activity |
The activity ID of the version from which you are copying appears by default. You can, however, select a new activity ID from the list of available choices. |
Copy Options |
Select a value to specify which information you want to copy to the new version for the particular activity: Labor and Non-labor (system default), Labor, Non-labor, or None. |
Copy |
Click to initiate the copy process. |
This section discusses how to copy projects.
Page Name |
Object Name |
Navigation |
Usage |
GM_BUD_PPSL_CPY |
|
Copy project information within the same proposal. |
To Proposal |
Displays the current proposal ID from which you are copying the project. You cannot change these fields. The new project must have the same proposal ID. To copy information from an entire proposal or a version, use the Copy Proposal page or the Copy Version page. |
To Version |
Displays the current version ID from which you are copying the project. You cannot change these fields. The new project must have the same version ID. |
To Start Date and To End Date |
The system populates the start and end dates of the project from which you are copying. You cannot change these fields. |
Project
From Project ID |
Indicates the value of the source project. |
To Project ID |
Displays the word NEXT. You cannot change the information in this field. When you click Copy, the system generates the next available project ID. |
Activity
From Activity |
Select this check box for all the activities that you want to copy to the new project. The system automatically selects all activities when you first access this page. |
To Activity |
The activity ID of the project from which you are copying appears by default. You can, however, select a new activity ID from the list of available choices. |
Copy Options |
Select a value to specify which information you want to copy to the new project for the particular activity: Labor and Non-labor (system default), Labor, Non-labor, or None. |
Copy |