This chapter provides overviews of pricing government contracts and discusses how to:
Price amount-based contract lines.
Price rate-based contract lines.
Pricing government contracts is the process of allocating fixed amounts to amount-based contract lines and associating rates to rate-based contract lines. Before a contract can be activated, you must allocate any fixed amount defined for a contract across all amount-based contract lines. Before you can bill or recognize revenue for rate-based contract lines, you must first define your rate and fee structure and associate it to your rate-based contract lines to enable the system to generate appropriate billable and revenue amounts for processing.
This section discusses:
Amount-based pricing.
Rate-based pricing.
Contract line changes on a pending contract.
After you define your government contract and add the products that make up your contract, the next step is to allocate the contract's fixed price amount across any eligible amount-based contract lines. A contract cannot be set to an active processing status until the fixed price amount has been properly allocated and the allocation option on the Amount Allocation page has been set to Complete. The contract must have a processing status of Active to bill and recognize revenue for your contract lines.
To allocate your amount-based contract line amounts, you use the Amount Allocation page. Both amount-based and rate-based contract lines appear on this page, but amount allocation only applies to amount-based contract lines. Rate-based contract lines appear as display only. If your contract only contains rate-based contract lines, amount allocation is not required, and you do not need to perform this step to activate your contract.
After the amount allocation is complete, the allocation option is set to Complete, and the Amount Allocation page is saved, the summarized fixed price total is displayed on the Contract-General page in the Fixed Price field. Any changes to this value must be completed using the amount allocation page, if the contract is in a pending processing status. After the contract is in an active processing status, any changes to the fixed price amount must be completed using amendment processing.
See Amending a Contract.
See Also
This section discusses:
Defining rate sets for rate-based contract lines.
Defining rate sets and rate plans for cost-plus contract lines.
You do not allocate amounts for rate-based contract lines or rate-based contract lines associated with a fee type (cost-plus). Rate-based contract lines are priced using Project Costing rate sets and rate plans. Rate sets and rate plans can be defined for general use or for a specific contract. Once defined, you assign the rate set or rate plan to the rate-based contract using the Related Projects page.
Only one rate set or rate plan can be assigned to a single rate-based contract line at any particular point in time. Rate sets enable you to define how specific contract line-related transactions are priced for costing, billing, and revenue recognition. Rate plans enable you to combine multiple rate sets together to perform more complex pricing scenarios.
When defining a rate set, you assign a rate definition type of Cost, Billing, or Revenue. This determines the type of pricing that is performed for the contract line transactions. Depending on whether your contract contains rate-based (no fee), cost-plus contract lines, or some combination of both, determines the types of rate sets and rate plans that must be defined.
Defining Rate Sets for Rate-Based Contract Lines
Rate-based contract lines that are assigned a fee type of None require a rate set with a Billing rate definition type. After you define the rate set, you assign the rate set to the contract line on the Related Projects page. After the contract is active and transactions are priced for this contract line, the system creates billable rows based on the criteria defined in the rate set.
The billable rows are stored in Project Costing, and passed to Billing by Contracts when the Contracts/Billing Interface (CA_BI_INTFC) process is run. Once finalized, the billed data is passed back to Contracts and Project Costing. These same transaction rows are also used for revenue recognition when the As-Incurred Revenue (PSA_ACCTGGL) process is run.
Defining Rate Sets and Rate Plans for Cost-Plus Contracts Lines
Rate-based contract lines that are assigned a fee type of Fixed, Award, Incentive or Other are cost-plus contract lines, and often require a more complex rate structure. Because cost-plus contract lines frequently require you to calculate indirect costs and may also require separate rates for billing and revenue pricing, you may need to define rate sets with rate definition types of Cost, Billing and Revenue.
Because you can assign only one rate set to a contract line, you must first define your rate sets, and then combine them onto a rate plan. The order that the rate sets are entered onto the rate plan is the same order that the system uses to perform pricing, enabling you to create rate stacking in situations where it is needed. The rate plan is assigned to the contract line on the Related Projects page, and enables you to implement as complex a pricing structure as you require.
When transactions are priced, indirect costs are calculated using the costing rate set, billable rows are created using the billing rate set, and if separate revenue rates are defined, then revenue rows are created using the revenue rate set.
See Also
Pricing Cost-Plus Contract Lines
After creating your contract, adding your contract lines, and assigning rate sets or rate plans to your rate-based contract lines, or performing amount allocation across your amount based contract lines, any changes that you need to make to the pricing structure is controlled by the processing status of the contract.
If the contract is in a Pending processing status, you can change your fixed amount contract totals, delete or add contract lines, and reallocate any amount changes across the amount-based contract lines. If different rate sets or rate plans are needed for your rate-based contract lines, you can update the Related Projects page with any changes that you need.
However, once the contract is in an Active processing status, any changes made to the pricing structure for amount-based contract lines must be made using amendment processing. If billing or revenue recognition has occurred against the contract lines impacted by the needed changes, then potentially, you may also need to cancel contract lines, or reverse billing or revenue when applying your pricing changes. Changes to the pricing structure for rate-based contract lines can be made outside of amendment processing.
See Managing Government Contracts.
This section discusses how to allocate amounts.
Page Name |
Object Name |
Navigation |
Usage |
|
Allocate fixed contract amounts across amount-based contract lines. |
Access the Amount Allocation page.
Fixed Price |
Enter the sum total of all amount-based contract lines associated with this contract. This amount may display by default using the total of the Extended Price associated with the amount-based contract lines. When allocating the total fixed price contract amount across all amount-based contract lines, you must balance to the amount listed in this field. |
Net Amount |
Displays the total fixed price amount for the contract. For government contracts, this field displays the Fixed Price total. |
Unallocated Amount |
Displays the fixed amount that has yet to be allocated across eligible amount-based contract lines. This amount must equal zero before you can set the allocation option to Complete. |
Inclusive Prepaids |
Displays any prepaid amounts defined for the contract. Prepaid amounts are defined using the Prepaids component (CA_PPD_BY_CONTRACT). Prepaid amounts can be inclusive or non-inclusive. Only inclusive prepaid amounts display on the Amount Allocation page and are included in the overall fixed price amount of the contract. |
Allocation |
Select the status of amount allocations. Values include:
Government contracts that contain amount-based contract lines must have the fixed amount for the contract completely allocated across any amount-based contract lines assigned to the contract and have the Allocation option set to Complete before the contract can be activated. |
Recalculate |
Click to update the Allocated Amount field with the amounts that have been allocated across amount-based contract lines. This button also automatically updates the allocation status to Complete when the unallocated amount equals zero. |
Contract Line Pricing
Line # (line number) |
Displays the contract line number assigned to the contract line when it was added to the contract. |
Product |
Displays the product identifier associated with the product when it was defined on the Product Definition page. |
Price Type |
Displays the price type associated with the product. For government contracts the only options that apply are the price types of Rate and Amount. |
Line Status |
Displays the status of the contract line. Only active amount-based contract lines are included in amount allocation. |
Quantity |
Displays the quantity associated with amount-based contract lines. |
Extended Price |
Displays the list price associated with amount-based contract lines. |
Fixed Price |
Enter the fixed amount total to be allocated to the amount-based contract line. |
Net Amount |
Displays the total allocated amount for the amount-based contract line. |
Line Totals
Fixed Price |
Displays the total allocated amount for all amount-based contract lines for the contract. |
Recalculate |
Click this button to recalculate any unallocated amounts, the net amount, line totals, fixed price amount and automatically update the allocation status to Complete when the unallocated amount is equal to zero. |
This section discusses how to:
Define rate sets.
Define rate set targets.
Define rate plans.
Page Name |
Object Name |
Navigation |
Usage |
|
Define the source criteria that is used to select the transactions from feeder systems to which the defined rate pricing structure will be applied. |
||
|
Define target data for rate set source rows. |
||
|
Create any combination of cost, billing, and revenue rate sets together to perform complex pricing scenarios. |
Access the Rate Sets page.
Business Unit |
Displays the Project Costing business unit. This is a required field and must be entered when creating a new rate set. |
Rate Set Type |
Displays the type of rate set. Values include:
|
Rate Definition Type |
Identify the types of rates in a rate set by entering the rate definition type. Rate definition types indicate to the system to use the rate set to create indirect costs from direct costs, price transactions for billing, or price transactions for revenue. Rate definition types are used to stack rate sets for more complex pricing scenarios. Select from one of the following rate definition types:
Note. After a rate set is created and saved, the rate definition type cannot be changed. To modify a rate definition type on a rate set, create a new rate set and assign the appropriate rate definition type. |
See Defining Standard or Contract-Specific Source Rows.
Access the Rate Sets - Target page.
The Rate Sets - Target page enables you to enter the target definitions for the source rows that you defined on the Rate Sets page. One source transaction row can have multiple target definition rows associated with it to enable you to track costs, indirect costs, billable rows, and so on depending on the type of rate set that you are defining.
See Defining Rate Set Target Rows.
Access the Rate Plans page.